I had them install two 1" conduits from the half bath electrical compartment to the storage bay below. I plan to install battery, solar, transfer switch monitors in the hall way wall. Half bath cabinet connects to the hall way wall so it should be easy. I was denied because they only do conduits horizontal because of slides. I emailed the president of engineering explaining it was 6' of conduit in a non sliding area and would take them anywhere in the cabinet to anywhere in the storage bay and was approved. Dealer didn't raise the price so don't think it is much. Won't know how it turned out until end of June.
__________________
2018 Dutch Star 4369 Spartan Chassis
2016 Jeep Cherokee, 1952 Willys CJ3A
|